Project story · Grand Junction, Colorado
CMU Library: From Shop Floor to a Three-Story Renovation
How Azar's Woodcraft coordinated custom millwork manufacturing and installation nearly four and a half hours from its facility.

More Than a Library Furniture Project
CMU Library in Grand Junction, Colorado, underwent a complete three-story renovation that included major structural repairs. The library was closed throughout construction. Azar’s Woodcraft manufactured and installed an extensive millwork package: circulation desks, shelving, built-ins, casework, architectural wall panels, end panels, trim, and window and door frames.

The Challenge of Working Four and a Half Hours Away
Our manufacturing facility in Erie was approximately 4½ hours from the jobsite. As construction progressed and areas became ready for our work, our team returned to the library for field measurements. We updated shop drawings to reflect actual building conditions rather than relying on original architectural plans alone.

Built and Checked in Our Shop
Back in Erie, we fabricated and fully assembled the millwork to verify fit, alignment and transitions before shipping. The circulation desk is a good example: its long sections and angled joints were brought together in our shop, then disassembled for transport to Grand Junction.



The Same Craftsmen Built It and Installed It
The shop staff who manufactured the millwork also traveled to CMU to install it. They knew how the assemblies were constructed and could make necessary onsite adjustments with firsthand knowledge of the details. That continuity mattered on a complex renovation far from our shop.

A Coordinated Weekly Process
Over approximately a year—perhaps a little less—our team repeated a carefully planned sequence: field measure, update drawings, fabricate, assemble in the shop, disassemble, load trucks, deliver weekly and install. While the onsite crew worked on one area, the shop prepared the next.

The Finished Library
The completed work ranged from circulation and service counters to integrated shelving, display cases, cabinetry and architectural wall treatments. Together, the project illustrates how careful field coordination, custom manufacturing and hands-on installation help bring a complex institutional interior together.

During the Renovation
A short video from the project site during the renovation.
More views of the finished library




From Manufacturing to the Finished Space
For this project, our responsibility extended well beyond producing individual components. Our team coordinated field conditions, shop drawings, fabrication, transportation and installation as the larger renovation progressed. The same people who built the millwork were there to fit it into the finished building.